ROADBUILDING – Hydraulic Rock Breaker
Truck Logger Magazine,
January issue, 1999
Case study – Cost-effective low-impact coastal Forest Road
construction
Construction
of the Buttle Bluffs main in the fall/winter of 1999, located in the Mount
Adrian area of central Vancouver Island required a narrow footprint with a
minimum of environmental and visual impact.
Road running width was kept at a minimum (yet ensuring user safety). To reduce the amount of disturbed ground absolute
control of the cut and fill slope angles were desired and these were kept to a
minimum as was the variable width right of way clearing.
Conventional
drilling and blasting would have required controlled blasting to control fly
rock and to control overbreak.
Techniques such as pre-shear holes, special explosives and the use of
blasting mats would have been needed to ensure control in the blasting
process.
End-haul
disposal sites were non-existent on the portion of the road constructed thru
Strathcona Park and would have involved high trucking costs as the nearest
disposal sites were some distance away.
TimberWest
chose the use of the hydraulic hammer instead of conventional drilling and
blasting for the Hammers ability to break rock without environmental
impact.
The
11,000 foot/lb G100 Rammer from Thiessen Equipment was mounted with a
quick-change on a Hitachi EX300LC excavator owned by Greg Bergeron of Eureka
Excavating Ltd. The Excavator was equipped with the standard Wajax “Roadbuilder
full bush guarding package”. Wayne
Cooledge of Wajax Equipment of Campbell River says “It was also equipped with
an extra 2000lb counterweight to counterbalance the hammer and was especially
plumbed to supply a balanced large hydraulic flow to the hammer by our shop
crew here in Campbell River” He also
stresses that the Wajax quick change (15-20min to change from the hammer to
either the dig or clean-up bucket) leaves the excavator truly versatile.
Hydraulic
hammer owner Greg Bergeron of Eureka Excavating Ltd states “I really believe in
them (the hammer) or I wouldn’t be in the business” and I also comments “(that) the hammer is the way its going to be
in the future”. He also feels that “In
the future there will be more manufacturers and suppliers of hammers.”
Paul
Berg, Superintendent of TimberWest comments “We were looking to save the costs
associated with endhauling”. “(The)
breaking up of the material to use as ballast and capping and (also) not
wasting time going back and drilling rock in the ditchlines was a money saver”
“The road was engineered to use the cut
material as balanced cuts and fills, (thereby) reducing lateral movement of
material” says Gary Veitch, RPF, Operations Engineer for TimberWest. “The rock
was weathered granitic material that stands up well when in place” “The hammer gave us more usable material
for ballast and on this particular job gave us better material”. “Personally I like the hammer for the
ditchline” says Gary. “The width and
shape can be exactly what you want without the possibility of fractured rock
from overblasting and the chance of mis-directed water” He also comments, “The hammer gives a nice
controlled cutslope without any excess material to be handled and eliminates the
problem of disposing (end-hauling) excess material from blasting
overbreak”.
“The
other hoe (TimberWest’s) with the dig bucket was going ahead and cold-decking
logs and pioneering where he could while I was doing ditchline” says Hydraulic
Hammer operator, Dave McVey of Campbell River. “When he came to an outcropping of rock and was rocked out we
would change places, and he would come back and excavate the material I had
broken up in the ditches and he used it to construct finished grade”
Dave
took care to make material selectively, larger material for subgrade and fines
for capping. The rock “broke well” says
Dave. Larger rock was especially made for armouring culvert outlets.
“Up
in that particular area it (the hammer) worked out exceptionally well” “It was the size of the hammer as well”,
“(it is) very effective”, “the G100 is
a very good breaker”
“I was pretty well impressed with it” says
TimberWest hoe operator Rob Hobenshield who was working in tandem with the
breaker. Rob is also a blaster and comments “There were also lots of large
boulders and the breaker dealt quicker with them than by drilling each one and
blasting it” He also notes that “we had
fallers working close by and blasting would have been limited to twice a day”
“We
also did not require a ballast crew”, notes Rob, which would have involved a
gravel pit or quarry with excavator for loading, trucks for hauling and a cat
for spreading.
TimberWest
Bullbucker Steve Telosky notes that the grade was steep in places (27%) with
some pretty generous cuts and that there was no rock wasted over the bank and
neither was any material trucked in either for ballast or capping eliminating
those potential costs.
It has long been known that the hammer has had a place in the past in sensitive or high-risk areas such as under powerlines, near highways, railways, creeks or lakes, or where vibration from blasting would be considered a hazard. TimberWest has not crunched the final numbers yet, but from indications given to this reporter, they appear pleasantly surprised by the apparent economy of the construction and the short construction time of this piece of road.
An
added advantage was the cost savings associated with allowing the falling and
road construction phases to continue uninterrupted while the hammer was
working. In a conventional situation,
the road building equipment along with the fallers would have to be moved out
for each blast.
Given
the apparent success, both environmentally and economically and of the short
project completion time, it would be easy to contemplate possible future
projects for the Hydraulic Hammer in Coastal Logging Road Construction.
=====================================================================
ADDITIONAL
DOCUMENT and CONTACT INFORMATION:
LICENSEE
Paul Berg, Operations
Superintendent
Gary Veitch, R.P.F.
Operations Engineer
TimberWest, Oyster
River Division - 250-287-8161
Road - Buttle Bluffs Main (BB Main)
Area – Mount
Adrian/Buttle Lake, Vancouver Island
EQUIPMENT OWNER
Greg Bergeron
Eureka Excavating
Ltd.
Box 277, Campbell River,
BC - 250 334 3755 or cel 250 203-1177
HAMMER OPERATOR
David McVey – 250
287-9930
Address – Campbell
River
HAMMER SUPPLIER
Thiessen Equipment
Limited, Noel McAuley - 604 514-8326
Website: www.thiessenteam.com
Email: thiessen@direct.ca
HAMMER MANUFACTURER
Make : Rammer
Model: G100
Breaking force:
11,000 pounds
Working weight,
kg 3800
Impact energy
according to CIMA method, J 5218
Impact rate,
bmp(beats per minute) 350-550
Acceptable oil flow,
l/min 220-350
Carrier minimum
pressure, bar 205
Hammer operating
pressure, bar 155-165
85 dB (A) level
distance, m 30-42
Carrier weight
limits, tons 40-70
Website: www.rammer.com
EXCAVATOR SUPPLIER
Wajax, Campbell
River,
Wayne Cooledge - 250
287-7177
Hitachi EX 300 LC –
Operating weight 77,000 lb.
Added counterweight –
2,000lb
Full bush guarding, Hydraulic
thumb, 2 buckets (Change from hammer to bucket in 15 minutes) High volume flow
plumbing for hammer. Tracks cut down to
26” width.
Website: www.wajax.com
Rob Hobenshield, Hoe
operator
Steve Telosky,
Bullbucker
TimberWest, Oyster
River Division - 250-287-8161
Eric L Kay, Forest
and Industrial Road Consultant - 250
337-5096
Black Creek, BC.
Email erickay@kayassociates.com
Website: www.kayassociates.com
TRUCK
LOGGER Magazine
Truck
Loggers Association
725-815
West Hastings
Vancouver,
BC, Canada V6C 1B4
Tel: 604 682-4080 (Lucy Butler)
Website: http://www.truckloggers.com/
Eric L Kay E Mail Forest Road Consultant
Back to Home Page - Kay & Associates